Stages of Construction
Slab Stage - Foundation poured (no forms) and lot is close to final grade.* Path for service lateral should be free from obstructions.**
Frame (or batterboard) Stage - House framed and lot close to final grade.* Path for service lateral should be free from obstructions.**
Brick Stage - House bricked and lot close to final grade.* Path for service lateral should be free from obstructions.**
Late Complete Stage - Driveway is poured or other obstructions** are usually in the pathway for service lateral construction. Lot is close to final grade.*
*If the final lot grade changes more or less than 8", the builder incurs the expense to re-bury service lateral according to specification.
** In most cases, builder will incur the expense to bore under obstructions for electric service.